Amendment #8 - Public Comment 3/8/10-3/22/10
|
|
Changes are as follows: Project # 213-05-0035 (Verot School Rd. & La. 92 Roundabout) Increasing from $525,000 to $931,436.
|
| |
Text : Documents
|
|
Amendment #7 - MPO Council Adopted 12/22/09
|
|
Changes are as follows: ARRA Project LA 733 (E. Broussard Rd.) from Jct. US 167(Johnston St.) - Jct. LA 92(E. Milton Ave.) Construction cost increasing from $4.486 Million to $5.643 Million.
|
| |
Text : Documents
|
|
Amendment #6 - MPO Council Adopted 12/22/09
|
|
Changes are as follows:
- Verot School Road Construction project (project # 828-12-0014) increasing from $17,200,000 to $25,231,000 as well as moving to the FY 11.
- Moving Project # 213-05-0035 (Roundabout at Verot School Rd.(La. 339) & Milton Rd. (La. 92)). Change from letting date of FY 08-09 to FY 09-10.
- ARRA Projects moved from FY 08-09 to FY 09-10.
- Exchanging Funding source of two ARRA projects (La. 93 @ La. 3168 Roundabout, and La. DOTD lighting Rehab.) for La. 733 (E. Broussard Rd.) Overlay.
- Adding $3,200,000 to La. DOTD's Demo fund for ROW acquisition for the I-49 Connector for FY 09-10.
|
| |
Text : Documents
|
| |
Maps and Graphics
|
|
Amendment #5 - MPO Council Adopted 7/28/09
|
|
Changes are as follows:
- South College from State to Local Funded Road
- $6 Million additional dollars for U.S. Hwy 90 Widening from Pinhook to LA 182 Interchange
- Bonin Rd. @ E. Milton Ave. (La. 92) Roundabout as a replacement ARRA project for La. 89 @ La. 92 Roundabout
- Verot School Rd. Project 828-12-0021 cost increasing from $6 million to $10 million
|
| |
Text : Documents
|
| |
Maps and Graphics
|
|
Amendment #4 - MPO Council Adopted 4/14/09
|
|
Changes are as follows: Addition of American Recovery and Reinvestment Act of 2009(ARRA) projects .
|
| |
Text : Documents
|
| |
Maps and Graphics
|
|
Amendment #3 - TPC Adopted 10/6/08
|
|
Changes are as follows: Reallocation of ($1,980,000) from I-49 lighting project 455-01-0048 to project 217-01-0017 La. 98 & La. 93 Roundabout ($500,000) project 455-01-0035 to I-49 Right of Way project (1,180,000) , project 700-28-0217 2030 Plan implementation ($150,000), and I-49 Action Plan ($150,000)
|
| |
Text : Documents
|
|
Amendment #2 - TPC Adopted 5/5/08
|
|
Changes are as follows: Addition of Scott Cities extension of Apollo Rd. from U.S. Hwy 90 to Dulles Dr. ($6,900,000) .
|
| |
Text : Documents
|
|
Amendment #1 - TPC Adopted 5/5/08
|
|
Changes are as follows: Addition of $20,000,000 for the Widening of U.S. Highway 90 (Pinhook to Albertson Parkway)
|
| |
Text : Documents
|
|
Original Information
|
|